A Realistic Construction Timeline for Common Remodels and Additions in the Pittsburgh Area
Determining a full timelinefor your home remodel is largely dependent on the scope of areas being renovated during the construction phase. Of course, the more areas needing planned for can extend your design timeline as well, but here are sometypical timelinesyou can count on when adding more rooms to your home remodel or addition project:
Kitchen and Great Room (12-16 weeks)
One of the top requested additions is to extend homes out the back on the first floor to make room for a bigger kitchen and great room with an open floor plan. These additions typically require 5-7 weeks during the construction phase.
Bathroom (2-4 weeks)
More bathroom space to accommodate growing children and guests is usually an add-on option for many home renovations. Depending on the size and scope of bathroom(s) being added or renovated, these could add an additional few weeks or a month to your construction timeline.
Master Bedroom and Ensuite (4-6 weeks)
Adding a second floor bedroom retreat with a larger bathroom and closet area is an appealing home addition option for growing families and even empty nesters looking to make use of their newly acquired space. The extent of demolition required may affect your timeline, but typically, you can count on adding 4-6 weeks for this portion of your project.
2-Story Rear Home Addition (12-18 weeks)
Cape Cod home architecture is plentiful in Pittsburgh. Many Cape Cod homeowners find a 2-story home addition at the rear of their home to be the best investment. They’re able to enlarge their kitchen, create a great room space with an open floor plan and then include a master bedroom and bathroom above. Some opt for a gameroom or, depending on their home’s existing space and their remodeling budget, more bedroom and bathroom spaces on the second floor. As the scope of a second story addition is so large, this timeline could require 12-18 weeks of construction.
2-Story Home Addition (16-24 weeks)
Second-story home additions prove beneficial for homeowners seeking additional living space upstairs, whether for a master suite, spare bedroom, extra bathroom, or storage/closet space. Action Builders facilitates the home addition process with easy communication, a straightforward design-build process, and quality work.The process of adding a second story involves removing the existing roof, planning stair placement, optimizing the main floor layout, and efficiently framing the second-story addition. Whether accommodating overnight guests or a growing family, a second-story addition is a versatile and aesthetically pleasing solution.